PLC Commissioning Checklist
A working checklist for controls engineers, integrators, and technicians commissioning a new or modified PLC program. Run it on screen during checkout or print it for the panel shop - the checkboxes work in your browser but are not saved between visits.
How to Use This Checklist
The checklist is organized as seven phases in the order most commissioning jobs actually run: preparation, pre-download checks, I/O checkout, communications, fail-state behavior, alarm and interlock testing, and handover. Work each phase to completion before moving on - most late-night commissioning problems trace back to a skipped item in an earlier phase.
Two ground rules. First, this page describes common practice, not requirements: your site procedures, permit system, and the equipment manufacturer's instructions always take precedence. Second, where a value is site-specific (test tolerances, setpoints, password policy), record what your site requires rather than inventing one on the spot.
Phase 1 - Preparation and Prerequisites
Everything in this phase happens before you connect a programming laptop to anything.
Phase 2 - Pre-Download Checks
Run these immediately before transferring the program to the controller.
Phase 3 - I/O Checkout
Isolate outputs from the process wherever actuation could cause harm, and clear each point one at a time against the I/O list.
Phase 4 - Communications Verification
Phase 5 - Fail-State Behavior
This is the phase most often skipped under schedule pressure, and the one that matters most at 2 AM.
Phase 6 - Alarm and Interlock Testing
Phase 7 - Documentation and Handover
Sources & Standards
This checklist reflects common commissioning practice. For the underlying standards and guidance:
- International Society of Automation (ISA) - standards covering instrumentation documentation, alarm management, and control system security that commissioning work touches.
- International Electrotechnical Commission (IEC) - publisher of the IEC 61131 series covering programmable controllers and their programming languages.
- NIST SP 800-82 Rev. 3 - the Guide to Operational Technology (OT) Security, relevant to controller access, network changes, and change management during commissioning.
A Second Set of Hands
This checklist is complete on its own - use it on your next startup. If you want help running it, Merobix does PLC programming and commissioning work alongside its monitoring platform.