Automation Glossary • Gas Nomination and Confirmation

What Is Gas Nomination and Confirmation?

Merobix Engineering • • 5 min read

Natural gas does not just flow wherever it likes on a pipeline - every unit that moves has been requested, scheduled, and agreed in advance through a process called nomination and confirmation. This is the daily paperwork of the gas business, the way a shipper tells the pipeline how much it intends to inject and withdraw and where. This guide explains the nomination and confirmation cycle, the timely, evening, and intraday windows that structure the gas day, and how live SCADA flow data lets operators reconcile what was scheduled against what actually delivered.

Back to Blog

Gas Nomination and Confirmation in one line: Gas nomination is a shipper's formal request to a pipeline to transport a specific quantity of gas from a named receipt point to a named delivery point for a given gas day. Confirmation is the responding step in which the parties at each end of the pipeline verify and agree to those quantities so the pipeline can schedule the flow. The cycle repeats on set windows through the gas day, and actual metered volumes are compared against the confirmed schedule to manage delivery.

The Nomination and Confirmation Cycle

A nomination is a shipper telling the pipeline, in effect, I want to put this much gas in here and take this much out there, under this contract, for this gas day. It names a receipt point where gas enters the pipeline, a delivery point where it leaves, a quantity, and the transportation contract that authorizes the move. Because a pipeline is a shared system with finite capacity, it cannot simply honor every request blindly; it collects nominations from all shippers and schedules flows that fit within the physical and contractual limits of each segment.

Confirmation is the handshake that turns a request into a scheduled flow. The pipeline sends the nominated quantities to the operators of the facilities at each end - the party delivering gas into the receipt point and the party taking gas at the delivery point - and asks them to confirm they agree with the volumes. Only confirmed quantities get scheduled. This step catches mismatches early: if a shipper nominates more into a point than the upstream party will actually deliver, or if a downstream party will not take the full amount, confirmation reveals the gap before the gas day begins rather than after imbalances have accumulated.

The Gas Day and Its Nomination Windows

Scheduling is organized around the gas day, a defined operational day that in North American practice runs from morning to morning rather than midnight to midnight. Within and around that day, nominations happen in structured cycles so the pipeline has time to process, confirm, and schedule. The timely cycle is the main deadline before the gas day starts and is where most volume is nominated. The evening cycle gives a later chance to nominate or adjust before flow begins. Once gas is flowing, intraday cycles allow shippers to change nominations partway through the day to respond to shifting supply and demand.

These windows exist because gas markets and physical conditions do not hold still. A shipper may find during the day that a well is producing more than expected, a plant is down, or downstream demand has jumped, and the intraday cycles let them bump or reduce their scheduled volumes accordingly rather than being locked to a number set the day before. Each cycle has its own deadline and its own effective time, so a nomination submitted in an intraday window takes effect from a specified hour, not retroactively. Understanding which cycle a change lands in is essential to knowing when the new flow is actually scheduled to take effect.

Reconciling Scheduled Against Actual with SCADA

A confirmed nomination is a plan, but gas is a physical commodity and reality never matches the plan exactly - meters run a little fast or slow, wells fluctuate, and demand moves. This is where live measurement matters. SCADA systems continuously read the actual metered flow at receipt and delivery points, so operators can compare what is physically moving against what was scheduled and confirmed, hour by hour, instead of waiting for a monthly statement to reveal how far off they ran.

A cloud SCADA platform such as Merobix supports this reconciliation by bringing real-time volumes from field meters into one view alongside the day's confirmed quantities, so a scheduler or operator can see a receipt point drifting above or below its nomination while there is still time to act. If flow is running short of the confirmed delivery, they can adjust operations or submit an intraday nomination in the next available cycle; if it is running long, they can trim it back before an imbalance builds. This is the practical link between the scheduling world of nominations and the physical world of metered gas: SCADA is what lets an operator manage the difference in real time rather than discover it after the fact.

Frequently Asked Questions

What is the difference between a nomination and a confirmation?

A nomination is a shipper's request to the pipeline to move a specific quantity of gas from a receipt point to a delivery point for a gas day. A confirmation is the pipeline verifying those quantities with the operators at each end and getting their agreement before scheduling the flow. In short, the shipper nominates and the connected parties confirm, and only confirmed volumes get scheduled.

What are the timely, evening, and intraday nomination cycles?

They are the scheduled windows for submitting or changing nominations around the gas day. The timely cycle is the primary deadline before the gas day starts, the evening cycle offers a later chance to nominate before flow begins, and the intraday cycles let shippers adjust volumes after gas is already flowing. Each cycle has its own deadline and effective time.

How does SCADA data relate to nominations?

SCADA provides the actual metered flow that operators compare against the confirmed nomination. Because physical flow never matches the schedule exactly, real-time measurement lets a scheduler see whether a point is running above or below its nominated volume and adjust operations or submit an intraday nomination while there is still time, rather than finding the imbalance at month-end.

From Definitions to a Live Dashboard

Merobix reads your field devices into a cloud SCADA - the real thing behind these terms, live in days from any browser.

Request a Free Demo +1 (903) 307-7300
More in Automation Glossary
Operational Balancing Agreement (OBA)  •  Lost and Unaccounted-For Gas (LUF)  •  Gas Imbalance Statement  •  Turboexpander (Gas Plant)  •  Demethanizer Column  •  NGL Fractionation  •  All Automation Glossary →