Texas RRC Statewide Rule 32 Flaring Explained

Merobix Engineering • • 5 min read

In Texas, the question of whether you can flare or vent gas from a well runs through the Railroad Commission's Statewide Rule 32, and operators who treat flaring as automatically allowed can find themselves out of compliance. This page explains, at a practitioner level, what Rule 32 governs, when an operator needs authorization to flare or vent, and how metering data supports the compliance story. It defers to qualified regulatory personnel on the rule's exact requirements and to the current rule text for specifics.

Back to Blog

RRC Statewide Rule 32 in one line: Statewide Rule 32 is the Texas Railroad Commission rule governing the flaring and venting of natural gas. It generally limits the release of gas by flaring or venting and requires operators to have authorization to do so beyond narrow allowances, so flaring is treated as something to be limited and justified rather than assumed. Operators demonstrate compliance partly through metering and reporting of the gas flared or vented.

What Rule 32 Governs

Statewide Rule 32 addresses the disposition of natural gas that is flared or vented rather than sold, used, or otherwise conserved. Its orientation is toward limiting the release of gas: gas is a resource the state has an interest in conserving, and flaring or venting it is treated as a loss to be constrained and accounted for, not a free default. That framing is the key mental shift for an operator used to thinking of flaring as simply what you do with gas you cannot sell.

The rule interacts with the broader authority of the Railroad Commission over oil and gas production in Texas, described in the explainer on the Texas Railroad Commission. Rule 32 is the specific flaring and venting piece of that authority, sitting alongside the state's interest in preventing waste of the resource. Because it is a state rule, it applies in addition to any federal expectations about associated gas, discussed in the guide on OOOOb associated gas flaring limits.

For an operator, the practical takeaway is that a well producing gas that is being flared or vented is operating under Rule 32, and the operator needs to understand what allowance or authorization covers that release. Assuming flaring is permitted without confirming the basis is the error the rule is written to prevent, and it is one that surfaces during a review of a well's disposition records.

When Authorization Is Needed and How Data Supports It

The rule contemplates limited circumstances where flaring or venting is allowed without special authorization - for example short-duration situations tied to well operations - and beyond those, an operator needs the Commission's authorization to continue flaring or venting. So the compliance question for a well is: does the flaring fit within an allowance, or does it require and have an authorization? Operators should determine which applies for each situation with qualified personnel and against the current rule.

Whatever the basis, the gas being flared or vented generally has to be measured and reported, which makes metering central to Rule 32 compliance. Knowing the volume flared over time is what lets an operator report accurately and stay within any authorized limit, and it is the objective evidence behind the disposition claimed for the gas. The instrument behind this is covered in the explainer on the flare gas flow meter, and the accounting in the explainer on lease fuel and flare accounting.

A cloud SCADA platform such as Merobix supports this by trending flare gas flow and flame status and retaining the history, so the volume flared and the periods of flaring are captured as data rather than estimated after the fact. That record underpins the state reporting described in the explainer on the flaring and venting report and gives the operator a defensible basis for the disposition reported for each well's gas.

Frequently Asked Questions

Do I need authorization to flare gas in Texas?

Often, yes, beyond narrow allowances. Statewide Rule 32 generally limits flaring and venting of natural gas and treats it as something to be constrained and justified rather than assumed. The rule contemplates limited circumstances where flaring is allowed without special authorization, typically short-duration situations tied to well operations, and beyond those an operator needs the Railroad Commission's authorization to continue. Which basis applies to a given well should be determined with qualified regulatory personnel against the current rule, because assuming flaring is permitted without confirming the basis is a common compliance error.

What is the purpose of Statewide Rule 32?

To govern and limit the flaring and venting of natural gas in Texas, reflecting the state's interest in conserving the resource and preventing its waste. The rule treats gas that is flared or vented rather than sold or used as a loss to be constrained and accounted for, so flaring is not a free default. It sits within the Railroad Commission's broader authority over oil and gas production and works alongside federal expectations about associated gas, so an operator flaring in Texas is typically satisfying both a state and a federal concern about routine flaring.

How does metering support Rule 32 compliance?

The gas being flared or vented generally has to be measured and reported, so metering is central to demonstrating compliance. Knowing the volume flared over time lets an operator report accurately, stay within any authorized limit, and provide objective evidence for the disposition claimed for the gas. Trending flare gas flow and flame status and retaining that history turns the flaring record into data rather than an after-the-fact estimate, giving the operator a defensible basis for the volumes reported and the periods of flaring on each well.

More in General Automation Concepts
RRC Flaring Exception Filing  •  ISA-5.1 line and signal types  •  Gas Capture Percentage (Flaring)  •  IEC 60584 thermocouple tolerance classes  •  IEC 60751 RTD tolerance classes  •  All General Automation Concepts →
Free SCADA operator training
Merobix University - 70 video lessons & 261 quiz questions, from first login to compliance reporting. No demo call required.
Start free →